How many 50 kg bags of cement are required for 1 cubic meter of concrete? (Concrete mix ratio= 1:1.5:3)
- Concrete mix ratio= 1:1.5:3 [Cement: Fine Aggregate: Coarse Aggregates]
- Unit Weight of Cement= 1440 kg/m³.
- Shrinkage Factor or Factor of Safety to Counter Shrinkage (Dry Volume / Wet Volume)= 54%, (Range 54 to 57%).
For 1 m³ Wet Concrete:
- Total Volume of Dry Concrete= 1 m³ Dry Concrete + 54% = 1 m³ + 0.54 m³ = 1.54 m³.
- Total Ratio = 1+1.5+3 = 5.5
- Total Parts of Cement for 1m³ Concrete= (Ratio of Cement/Total Ratio of Concrete)x1.54 = (1/5.5)x1.54= 0.28m³
- So, Total volume of Cement= 0.28x Unit Weight of Cement= 0.28 m³x 1440 kg/m³= 403.2 kg.
- Number of Cement Bags= 403.2/50= 8.064 Bags ≈ 8 Bags