The minimum period for removing formwork

In normal circumstances, the ambient temperature does not fall below 15 C, ordinary Portland cement is used, and adequate curing is done, following period is acceptable.

Part of Structure

The minimum period for removing formwork

Sides of foundations, columns, beams and walls

24 hours

 

Under sides of slabs of up to 4.5 metre span

7 days

 

Under sides of slabs of above 4.5 metres span and under sides of beams and arches up to 6 metres span

14 days

 

Under sides of beams and arches over 6 metres  span and up to 9 metres span

21 days

Cantilever slabs and beams 

21 days

Domes, shells and other structures of special nature

As per written instructions of officer-in-charge.


The officer-in-charge may however extend the periods noted where necessary by giving written instructions to the contractor.