The minimum period for removing formwork
In normal circumstances, the ambient temperature does not fall below 15 C, ordinary Portland cement is used, and adequate curing is done, following period is acceptable.
|
Part of
Structure |
The minimum
period for removing formwork |
|
Sides of
foundations, columns, beams and walls |
24 hours |
|
Under sides
of slabs of up to 4.5 metre span |
7 days |
|
Under sides of
slabs of above 4.5 metres span and under sides of beams and arches up to 6
metres span |
14 days |
|
Under sides
of beams and arches over 6 metres span
and up to 9 metres span |
21 days |
|
Cantilever
slabs and beams |
21 days |
|
Domes, shells
and other structures of special nature |
As per
written instructions of officer-in-charge. |
The officer-in-charge may however extend the periods noted where necessary by giving written instructions to the contractor.